Campus Impact Committee
Construction Projects Update -- August 23, 2023
Project | Start | End | Description |
Joan Perry Brock Center | May 2021 | Grand Opening August 25 |
Convocation, sports, and events center |
Eason Hall Elevator | December 2023 | January 2024 | Replace elevator cab. The elevator will be unavailable during this period, but the Project Manager is working to provide alternatives. |
Replacement Facilities Building | January 3, 2023 | late summer 2024 | Renovate and expand the former Lumberyard building on Fourth Street for Facilities, EHS, Space Planning, and Construction Departments. The entrance to the Virginia Street Parking Lot is blocked; access is via the connection to the Putney Street Parking Lot |
Maugans Sanitary Sewer Line | not earlier than winter break |
January 2024 | Replace the existing sanitary sewer line on the south side of Maugans Alumni Center from Beale Plaza to the driveway to Tabb Circle. |
Hiner Fan Coil Units (FCUs) | May 22, 2023 | September 2023 | Replace the existing HVAC FCUs throughout the building. Currently dealing with a unit control issue. |
East Madison Street Steam Lines | July 17, 2023 | October 2023 | Replace the existing steam and condensate lines under the street and repave the work area. |