Campus Impact Committee
Construction Projects Update -- May 24, 2023
Project | Start | End | Description and Comments |
---|---|---|---|
Joan Perry Brock Center | May 2021 | September 2023 | Convocation, sports, and events center |
Eason Hall Elevator | December 2023 | January 2024 | Replace elevator cab. The elevator will be unavailable during this period, but the Project Manager is working to provide alternatives. |
Replacement Facilities Building | January 3, 2023 | late summer 2024 | Renovate and expand the former Lumberyard building on Fourth Street for Facilities, EHS, Space Planning, and Construction Departments. The entrance to the Virginia Street Parking Lot is blocked; access is via the connection to the Putney Street Parking Lot. |
Maugans Sanitary Sewer Line | late summer 2023* | fall 2023* | Replace the existing buried sanitary sewer line on the south side of Maugans Alumni Center from Beale Plaza to the driveway to Tabb Circle. *There is a high probability that the project will not start until holiday break 2023. |
Hiner Fan Coil Units (FCUs) | May 22, 2023 | late summer 2023 | Replace the existing HVAC FCUs throughout the building. Parking spaces (except ADA) behind Hiner and Coyner will be unavailable. Cooling will be shut down periodically by floors throughout the summer. |