Project | Start | End | Description and Comments |
---|---|---|---|
Joan Perry Brock Center | May 2021 | Summer 2023 | Convocation, sports, and events center |
Eason Hall Elevator | Early Summer 2023 (tentative) |
Late Summer 2023 (tentative) |
Replace elevator cab. The start date is dependent on the arrival of parts and materials. The elevator will be unavailable during this period, but the Project Manager is working to provide alternatives. |
Replacement Facilities Building | January 3, 2023 | Late Summer 2024 | Renovate and expand the former Lumberyard building on Fourth Street for Facilities, EHS, Space Planning, and Construction Departments. The entrance to the Virginia Street Parking Lot is blocked; access is via the connection to the Putney Street Parking Lot. |
Greenwood Cooling Tower | November 28, 2022 | Late February 2023 | Refurbish the cooling tower. Additional repair work will occur in mid to late February. Several parking spaces in the Library Parking Lot will be blocked. |